West Anglia Connection Node E 400kV: grid connection queue
West Anglia Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 800 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pelham 400 | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| TH Stocking Pelham | FRV Powertek Limited | Battery storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Pelham 400 | 30 Oct 2033 | 31 Oct 2034 | +12 months |
| 13 Oct 2026 | Pelham 400 | 31 Oct 2034 | 30 Oct 2033 | -12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Longstanton Primary 11kV | UK Power Networks | 4.2 km | 22 MW | 8.4 MW |
| St Ives Primary 11kV | UK Power Networks | 6.4 km | 12 MW | 12 MW |
| Aldreth Primary 11kV | UK Power Networks | 8.9 km | 19 MW | -0.7 MW |
| Histon Grid 33kV | UK Power Networks | 9.3 km | 38 MW | 58 MW |
| Histon Primary 11kV | UK Power Networks | 9.3 km | 12 MW | 8 MW |
| Hilton Primary 11kV | UK Power Networks | 9.6 km | 1.7 MW | 1.7 MW |
Thinking of connecting near West Anglia Connection Node E 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node A 400kV: 1,600 MW waiting
- WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION: 1,250 MW waiting
- West Anglia Connection Node F 400kV: 3,429 MW waiting
- Eaton Socon 400kV: 1,550 MW waiting
- West Anglia Connection Node C 400kV: 2,050 MW waiting