West Anglia Connection Node G 400kV: grid connection queue

West Anglia Connection Node G 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,920 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

3projects in the queue
1,920 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Spalding High Impact Energy HubTELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2034Low31 Oct 2034Scoping1
Astwood Solar Farm GECASTWOOD GREEN ENERGY LTDSolar + storage52031 Oct 2034Low31 Oct 2034Scoping1
Ryhall PV & BESSKilnside Energy Park LimitedSolar + storage40031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
3 Nov 2026Astwood Solar Farm GEC31 Oct 203731 Oct 2034-36 months
13 Oct 2026Astwood Solar Farm GEC31 Oct 203431 Oct 2037+36 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Offord Primary 11kVUK Power Networks3.9 km11 MW9.3 MW
Perry Primary 11kVUK Power Networks4.1 km10 MW4 MW
Godmanchester Primary 11kVUK Power Networks6.2 km2.8 MW4.2 MW
Huntingdon Grid 11kVUK Power Networks6.7 km105 MW25 MW
Huntingdon Grid 33kVUK Power Networks6.7 km62 MW51 MW
Cotton Primary 11kVUK Power Networks6.9 km4.7 MW4.2 MW

Thinking of connecting near West Anglia Connection Node G 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points