West Anglia Connection Node H 400kVSubstation: grid connection queue

West Anglia Connection Node H 400kVSubstation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 2,000 MW are waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

2projects in the queue
2,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Huntingdon High Impact Energy Hub 1TELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2034Low31 Oct 2034Awaiting Consents1
Huntingdon High Impact Energy Hub 2TELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Perry Primary 11kVUK Power Networks4.8 km10 MW4 MW
Little Barford 11kVUK Power Networks6.8 km37 MW7 MW
Little Barford 33kVUK Power Networks6.8 km30 MW37 MW
Kimbolton Primary 11kVUK Power Networks7.0 km1.9 MW-0.2 MW
Offord Primary 11kVUK Power Networks8.9 km11 MW9.3 MW
Cotton Primary 11kVUK Power Networks10.9 km4.7 MW4.2 MW

Thinking of connecting near West Anglia Connection Node H 400kVSubstation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points