Grendon 400kV: grid connection queue

Grendon 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Jul 2029 to 1 Jul 2029.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Grendon Solar & BESSGreen Hill Solar Farm LimitedSolar + storage5001 Jul 2029Medium1 Jul 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Manton Ln Primary 11kVUK Power Networks1.0 km21 MW5 MW
Prebend St Primary 11kVUK Power Networks2.6 km45 MW16 MW
Austin Canons Primary 11kVUK Power Networks3.0 km26 MW1 MW
Austin Canons Grid 33kVUK Power Networks3.0 km118 MW28 MW
Harrowden Primary 11kVUK Power Networks4.6 km34 MW18 MW
Edison Rd Grid 11kVUK Power Networks4.8 km32 MW15 MW

Thinking of connecting near Grendon 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points