Marston Vale 400kV: grid connection queue
Marston Vale 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 539 MW are waiting to connect here (largest by capacity: gas and thermal, solar + storage). Contracted dates run from 28 Jun 2024 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Millbrook Power | MILLBROOK POWER LIMITED | Gas and thermal | 299 | 28 Jun 2024 | n/a | Under Construction/Commissioning | none | |
| Lightsource Marston Vale 240MW PV+BESS | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| West Bedford Primary 11kV | UK Power Networks | 1.7 km | 22 MW | 9.6 MW |
| Marston Rd Primary 11kV | UK Power Networks | 3.3 km | 6.7 MW | 2.7 MW |
| Marston Rd Grid 33kV | UK Power Networks | 3.4 km | 93 MW | 74 MW |
| Austin Canons Primary 11kV | UK Power Networks | 3.9 km | 26 MW | 1 MW |
| Austin Canons Grid 33kV | UK Power Networks | 3.9 km | 118 MW | 28 MW |
| Prebend St Primary 11kV | UK Power Networks | 4.8 km | 45 MW | 16 MW |
Thinking of connecting near Marston Vale 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Grendon 400kV: 500 MW waiting
- Grendon 132kV: 41 MW waiting
- LAVENDON 400KV SUBSTATION: 1,000 MW waiting
- Chiltern Connection Node D 400kV: 1,200 MW waiting
- West Anglia Connection Node I 400kV substation: 2,340 MW waiting