Chiltern Connection Node D 400kV: grid connection queue
Chiltern Connection Node D 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,200 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Oxfordshire Energy Park | Low Carbon Solar Park 40 Limited | Solar + storage | 500 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| West Oxfordshire Energy Park | LOW CARBON SOLAR PARK 43 LIMITED | Solar + storage | 500 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
| TH Didcot | FRV Powertek Limited | Battery storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Westoning Primary 11kV | UK Power Networks | 3.9 km | 23 MW | 8 MW |
| Westoning Grid 33kV | UK Power Networks | 4.0 km | 92 MW | 55 MW |
| Sundon Primary 11kV T1&T2 | UK Power Networks | 5.0 km | 8.8 MW | 22 MW |
| Sundon Primary 11kV T3&T4 | UK Power Networks | 5.0 km | 31 MW | 13 MW |
| Sundon 33kV | UK Power Networks | 5.2 km | 156 MW | 64 MW |
| Ampthill Primary 11kV | UK Power Networks | 6.8 km | 16 MW | 3.7 MW |
Thinking of connecting near Chiltern Connection Node D 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Sundon 400kV: 1,150 MW waiting
- Chiltern Connection Node C 400kV: 1,500 MW waiting
- Dunstable 400kV: 1,930 MW waiting
- Chiltern Connection Node A 400kV: 750 MW waiting
- Marston Vale 400kV: 539 MW waiting