Chiltern Connection Node A 400kV: grid connection queue

Chiltern Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 750 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
750 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Didcot BESS 1Downing Renewable Developments LLPBattery storage75031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Leighton Buzzard Primary 11kVUK Power Networks5.1 km36 MW37 MW
Cheddington Primary 11kVUK Power Networks11.5 km6.6 MW0.7 MW
Pitstone Primary 11kVUK Power Networks13.4 km18 MW14 MW
East Claydon GSPSSEN Distribution13.7 km
Aylesbury East Grid 33kVUK Power Networks13.9 km97 MW23 MW
Buckingham Rd Primary 11kVUK Power Networks14.4 km16 MW8.2 MW

Thinking of connecting near Chiltern Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points