Sundon 400kV: grid connection queue
Sundon 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,150 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sundon | SUNDON BATTERY STORAGE LIMITED | Battery storage | 50 | 30 Apr 2027 | High | 29 Apr 2029 | Under Construction/Commissioning | 2 |
| Sundon Storage | Statera Energy Limited | Battery storage | 500 | 30 Oct 2027 | High | 29 Oct 2029 | Scoping | 1 |
| Fancott | KONA ASSET 2 LIMITED | Battery storage | 600 | 30 Oct 2031 | Medium | 30 Oct 2031 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Sundon | 5 Sep 2025 | 30 Apr 2027 | +20 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Leighton Buzzard Primary 11kV | UK Power Networks | 5.6 km | 36 MW | 37 MW |
| Sundon Primary 11kV T1&T2 | UK Power Networks | 6.3 km | 8.8 MW | 22 MW |
| Sundon Primary 11kV T3&T4 | UK Power Networks | 6.3 km | 31 MW | 13 MW |
| Sundon 33kV | UK Power Networks | 6.5 km | 156 MW | 64 MW |
| Houghton Regis Primary 11kV | UK Power Networks | 7.8 km | 46 MW | 5.5 MW |
| Houghton Regis Grid 33kV | UK Power Networks | 7.8 km | 102 MW | 39 MW |
Thinking of connecting near Sundon 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chiltern Connection Node D 400kV: 1,200 MW waiting
- Chiltern Connection Node C 400kV: 1,500 MW waiting
- Chiltern Connection Node A 400kV: 750 MW waiting
- Dunstable 400kV: 1,930 MW waiting
- Chiltern Connection Node B 400kV: 1,000 MW waiting