Benzene

Sundon 400kV: grid connection queue

Sundon 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,150 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Oct 2031.

3projects in the queue
1,150 MWwaiting to connect
50 MWalready connected
50 MWholding Gate 2
1date moves since 2 Jun 2026
550 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
SundonSUNDON BATTERY STORAGE LIMITEDBattery storage5030 Apr 2027High29 Apr 2029Under Construction/Commissioning2
Sundon StorageStatera Energy LimitedBattery storage50030 Oct 2027High29 Oct 2029Scoping1
FancottKONA ASSET 2 LIMITEDBattery storage60030 Oct 2031Medium30 Oct 2031Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
27 Oct 2026Sundon5 Sep 202530 Apr 2027+20 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Leighton Buzzard Primary 11kVUK Power Networks5.6 km36 MW37 MW
Sundon Primary 11kV T1&T2UK Power Networks6.3 km8.8 MW22 MW
Sundon Primary 11kV T3&T4UK Power Networks6.3 km31 MW13 MW
Sundon 33kVUK Power Networks6.5 km156 MW64 MW
Houghton Regis Primary 11kVUK Power Networks7.8 km46 MW5.5 MW
Houghton Regis Grid 33kVUK Power Networks7.8 km102 MW39 MW

Thinking of connecting near Sundon 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points