Benzene

Dunstable 400kV: grid connection queue

Dunstable 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,930 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 31 Oct 2031 to 29 Oct 2032.

3projects in the queue
1,930 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Woburn Solar FarmSolarThree LtdSolar84031 Oct 2031Medium31 Oct 2031Scoping1
Hockliffe GEC (Ethos Green)HOCKLIFFE GREEN ENERGY CENTRE LTDSolar + storage85029 Oct 2032Low29 Oct 2032Scoping1
Hipsey BESSKONA ASSET 2 LIMITEDBattery storage24029 Oct 2032Low29 Oct 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Houghton Regis Primary 11kVUK Power Networks0.8 km46 MW5.5 MW
Houghton Regis Grid 33kVUK Power Networks0.8 km102 MW39 MW
Dunstable Primary 11kVUK Power Networks1.4 km23 MW4.8 MW
Lewsey Primary 11kVUK Power Networks1.9 km9.8 MW5.2 MW
Kensworth Primary 11kVUK Power Networks3.2 km5.8 MW1.8 MW
Chaul End Primary 11kVUK Power Networks3.6 km23 MW6.6 MW

Thinking of connecting near Dunstable 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points