Chiltern Connection Node C 400kV: grid connection queue
Chiltern Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,500 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Nov 2038 to 1 Nov 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| BF88 Oakley | BLUEFIELD RENEWABLE DEVELOPMENTS LIMITED | Solar + storage | 1,000 | 1 Nov 2038 | Low | 1 Nov 2038 | Scoping | 1 |
| Ludgershall - Bicester Solar Farm PVDP | SolarFour Ltd | Solar + storage | 500 | 1 Nov 2038 | Low | 1 Nov 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dunstable Primary 11kV | UK Power Networks | 3.9 km | 23 MW | 4.8 MW |
| Houghton Regis Primary 11kV | UK Power Networks | 4.2 km | 46 MW | 5.5 MW |
| Houghton Regis Grid 33kV | UK Power Networks | 4.2 km | 102 MW | 39 MW |
| Kensworth Primary 11kV | UK Power Networks | 4.7 km | 5.8 MW | 1.8 MW |
| Lewsey Primary 11kV | UK Power Networks | 5.6 km | 9.8 MW | 5.2 MW |
| Leighton Buzzard Primary 11kV | UK Power Networks | 5.8 km | 36 MW | 37 MW |
Thinking of connecting near Chiltern Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Dunstable 400kV: 1,930 MW waiting
- Sundon 400kV: 1,150 MW waiting
- Chiltern Connection Node D 400kV: 1,200 MW waiting
- Chiltern Connection Node B 400kV: 1,000 MW waiting
- Chiltern Connection Node A 400kV: 750 MW waiting