Chiltern Connection Node C 400kV: grid connection queue

Chiltern Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,500 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Nov 2038 to 1 Nov 2038.

2projects in the queue
1,500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
BF88 OakleyBLUEFIELD RENEWABLE DEVELOPMENTS LIMITEDSolar + storage1,0001 Nov 2038Low1 Nov 2038Scoping1
Ludgershall - Bicester Solar Farm PVDPSolarFour LtdSolar + storage5001 Nov 2038Low1 Nov 2038Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dunstable Primary 11kVUK Power Networks3.9 km23 MW4.8 MW
Houghton Regis Primary 11kVUK Power Networks4.2 km46 MW5.5 MW
Houghton Regis Grid 33kVUK Power Networks4.2 km102 MW39 MW
Kensworth Primary 11kVUK Power Networks4.7 km5.8 MW1.8 MW
Lewsey Primary 11kVUK Power Networks5.6 km9.8 MW5.2 MW
Leighton Buzzard Primary 11kVUK Power Networks5.8 km36 MW37 MW

Thinking of connecting near Chiltern Connection Node C 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.