Chiltern Connection Node C 132kV: grid connection queue
Chiltern Connection Node C 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Nov 2038 to 1 Nov 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Witney BESS | Voltwise Power Holdings Limited | Battery storage | 150 | 1 Nov 2038 | Low | 1 Nov 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Buckingham Rd Primary 11kV | UK Power Networks | 5.8 km | 16 MW | 8.2 MW |
| Aylesbury East Grid 33kV | UK Power Networks | 6.4 km | 97 MW | 23 MW |
| Exchange St Primary 11kV | UK Power Networks | 7.6 km | 59 MW | 14 MW |
| Coldharbour Farm 11kV | UK Power Networks | 7.9 km | 14 MW | 9 MW |
| Arla Dairies Primary 11kV | UK Power Networks | 8.8 km | 16 MW | 18 MW |
| North Dr Primary 11kV | UK Power Networks | 8.9 km | 16 MW | -3.6 MW |
Thinking of connecting near Chiltern Connection Node C 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chiltern Connection Node A 400kV: 750 MW waiting
- Chiltern Connection Node B 400kV: 1,000 MW waiting
- Chiltern Connection Node C 400kV: 1,500 MW waiting
- Sundon 400kV: 1,150 MW waiting
- Amersham Main 400kV: 250 MW waiting