Yaxley 400kV: grid connection queue

Yaxley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 998 MW are waiting to connect here (largest by capacity: solar + storage, gas and thermal). Contracted dates run from 28 Jun 2024 to 31 Oct 2031.

3projects in the queue
998 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Progress Power StationPROGRESS POWER LIMITEDGas and thermal29928 Jun 2024n/aUnder Construction/Commissioningnone
EcoYaxley1Ecopower Suffolk LtdSolar + storage24930 Dec 2030Medium30 Dec 2030Scopingnone
Yaxley GEC (Ethos Green)YAXLEY GREEN ENERGY CENTRE LTDSolar + storage45031 Oct 2031Medium31 Oct 2031Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Farcet Primary 11kVUK Power Networks2.9 km12 MW10 MW
Peterborough South Grid 11kVUK Power Networks5.2 km106 MW34 MW
Peterborough South Grid 33kVUK Power Networks5.2 km1.4 MW67 MW
Orton Primary 11kVUK Power Networks5.5 km1.4 MW8.2 MW
Peterborough Central 11kVUK Power Networks6.2 km32 MW13 MW
Peterborough Central 33kVUK Power Networks6.2 km69 MW76 MW

Thinking of connecting near Yaxley 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.