Yaxley 400kV: grid connection queue
Yaxley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 998 MW are waiting to connect here (largest by capacity: solar + storage, gas and thermal). Contracted dates run from 28 Jun 2024 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Progress Power Station | PROGRESS POWER LIMITED | Gas and thermal | 299 | 28 Jun 2024 | n/a | Under Construction/Commissioning | none | |
| EcoYaxley1 | Ecopower Suffolk Ltd | Solar + storage | 249 | 30 Dec 2030 | Medium | 30 Dec 2030 | Scoping | none |
| Yaxley GEC (Ethos Green) | YAXLEY GREEN ENERGY CENTRE LTD | Solar + storage | 450 | 31 Oct 2031 | Medium | 31 Oct 2031 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Farcet Primary 11kV | UK Power Networks | 2.9 km | 12 MW | 10 MW |
| Peterborough South Grid 11kV | UK Power Networks | 5.2 km | 106 MW | 34 MW |
| Peterborough South Grid 33kV | UK Power Networks | 5.2 km | 1.4 MW | 67 MW |
| Orton Primary 11kV | UK Power Networks | 5.5 km | 1.4 MW | 8.2 MW |
| Peterborough Central 11kV | UK Power Networks | 6.2 km | 32 MW | 13 MW |
| Peterborough Central 33kV | UK Power Networks | 6.2 km | 69 MW | 76 MW |
Thinking of connecting near Yaxley 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Anglia Connection Node C 400kV: 2,050 MW waiting
- West Anglia Connection Node A 400kV: 1,600 MW waiting
- West Anglia Connection Node G 400kV: 1,920 MW waiting
- Eaton Socon 400kV: 1,550 MW waiting
- Ryhall 400kV: 790 MW waiting