Ryhall 400kV: grid connection queue
Ryhall 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 790 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 1 Jan 2028 to 30 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Essendine | MALLARD PASS SOLAR FARM LIMITED | Solar | 240 | 1 Jan 2028 | High | 15 Jan 2030 | Consents Approved | none |
| Graeme Road Solar & BESS | GREENTECH PROJECTS HOLDING UK LIMITED | Solar + storage | 550 | 30 Oct 2038 | Low | 30 Oct 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Peterborough North Grid 11kV | UK Power Networks | 17.1 km | 107 MW | 23 MW |
| Orton Primary 11kV | UK Power Networks | 19.5 km | 1.4 MW | 8.2 MW |
Thinking of connecting near Ryhall 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Yaxley 400kV: 998 MW waiting
- Weston Marsh 400kV: 2,730 MW waiting
- Spalding North 400kV: 550 MW waiting
- East Anglia Connection Node E 400kV: 500 MW waiting
- Navenby 132kV: 529 MW waiting