Ryhall 400kV: grid connection queue

Ryhall 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 790 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 1 Jan 2028 to 30 Oct 2038.

2projects in the queue
790 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
240 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
EssendineMALLARD PASS SOLAR FARM LIMITEDSolar2401 Jan 2028High15 Jan 2030Consents Approvednone
Graeme Road Solar & BESSGREENTECH PROJECTS HOLDING UK LIMITEDSolar + storage55030 Oct 2038Low30 Oct 2038Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Peterborough North Grid 11kVUK Power Networks17.1 km107 MW23 MW
Orton Primary 11kVUK Power Networks19.5 km1.4 MW8.2 MW

Thinking of connecting near Ryhall 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points