East Anglia Connection Node E 400kV: grid connection queue
East Anglia Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Manor Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Manor Farm | 30 Oct 2038 | 31 Oct 2034 | -48 months |
| 13 Oct 2026 | Manor Farm | 31 Oct 2034 | 30 Oct 2038 | +48 months |
Thinking of connecting near East Anglia Connection Node E 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Coddington 400kV: 2,240 MW waiting
- Navenby 132kV: 529 MW waiting
- Navenby 400kV: 4,370 MW waiting
- Ryhall 400kV: 790 MW waiting
- Trent Valley South Connection Node G 400kV: 400 MW waiting