Coddington 400kV: grid connection queue
Coddington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 2,240 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Sep 2033 to 30 May 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Newark BESS | SSE DE SOLAR HOLDCO LIMITED | Solar + storage | 600 | 30 Sep 2033 | Low | 30 Sep 2033 | Scoping | 1 |
| Mountain Fen | LIGHTSOURCE SPV 204 LIMITED | Battery storage | 240 | 30 Sep 2034 | Low | 30 Sep 2034 | Scoping | 1 |
| Navenby Farm | CODDINGTON 10 RENEWABLES LTD | Solar + storage | 1,000 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Tyler Hill Bicker Fen | FRV Powertek Limited | Battery storage | 400 | 30 May 2035 | Low | 30 May 2035 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Navenby Farm | 30 May 2034 | 30 Oct 2034 | +5 months |
| 13 Oct 2026 | Navenby Farm | 30 Oct 2034 | 30 May 2034 | -5 months |
Thinking of connecting near Coddington 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Burton 400kV: 1,080 MW waiting
- West Burton 132kV: 120 MW waiting
- Staythorpe 400kV: 1,637 MW waiting
- Staythorpe 400kv: 250 MW waiting
- High Marnham 400kV: 3,596 MW waiting