High Marnham 400kV: grid connection queue
High Marnham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
8 projects with 3,596 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2029 to 30 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| One Earth Solar Farm | ONE EARTH SOLAR FARM LIMITED | Solar + storage | 740 | 31 Oct 2029 | Medium | 31 Oct 2029 | Awaiting Consents | none |
| High Marnham (Tertiary) | ENSO GREEN HOLDINGS K LIMITED | Solar + storage | 57 | 31 Oct 2030 | Medium | 31 Oct 2030 | Consents Approved | 2 |
| High Marnham Solar Farm | ANESCO LIMITED | Solar | 100 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| High Marnham 400 | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 1,000 | 31 Oct 2033 | Low | 31 Oct 2033 | Awaiting Consents | none |
| Mosedale Energy | MOSEDALE ENERGY LIMITED | Battery storage | 249 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| Welbeck-Newark Solar Farm - PVDP | SolarTen Ltd | Solar + storage | 710 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| High Marnham BESS | JG PEARS GRID CONNECTION LIMITED | Battery storage | 500 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | none |
| Morton Manor PV & BESS Station | IB VOGT UK LTD | Solar + storage | 240 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 5 times: 3 later and 2 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | High Marnham Solar Farm | 1 Nov 2029 | 31 Oct 2031 | +24 months |
| 13 Oct 2026 | High Marnham Solar Farm | 31 Oct 2031 | 1 Nov 2029 | -24 months |
| 13 Oct 2026 | Morton Manor PV & BESS Station | 31 Oct 2037 | 30 Oct 2034 | -36 months |
| 13 Oct 2026 | Mosedale Energy | 31 Mar 2033 | 31 Oct 2033 | +7 months |
| 28 Jul 2026 | High Marnham (Tertiary) | 31 Oct 2029 | 31 Oct 2030 | +12 months |
Thinking of connecting near High Marnham 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Staythorpe 400kV: 1,637 MW waiting
- Staythorpe 400kv: 250 MW waiting
- Cottam 400kV: 2,100 MW waiting
- Trent Valley North Connection Node F 400kV: 1,000 MW waiting
- West Burton 400kV: 1,080 MW waiting