High Marnham 400kV: grid connection queue

High Marnham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

8 projects with 3,596 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2029 to 30 Oct 2034.

8projects in the queue
3,596 MWwaiting to connect
0 MWalready connected
57 MWholding Gate 2
5date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
One Earth Solar FarmONE EARTH SOLAR FARM LIMITEDSolar + storage74031 Oct 2029Medium31 Oct 2029Awaiting Consentsnone
High Marnham (Tertiary)ENSO GREEN HOLDINGS K LIMITEDSolar + storage5731 Oct 2030Medium31 Oct 2030Consents Approved2
High Marnham Solar FarmANESCO LIMITEDSolar10031 Oct 2031Medium31 Oct 2031Scoping1
High Marnham 400ENSO GREEN HOLDINGS X LIMITEDSolar + storage1,00031 Oct 2033Low31 Oct 2033Awaiting Consentsnone
Mosedale EnergyMOSEDALE ENERGY LIMITEDBattery storage24931 Oct 2033Low31 Oct 2033Scoping1
Welbeck-Newark Solar Farm - PVDPSolarTen LtdSolar + storage71030 Oct 2034Low30 Oct 2034Scoping1
High Marnham BESSJG PEARS GRID CONNECTION LIMITEDBattery storage50030 Oct 2034Low30 Oct 2034Scopingnone
Morton Manor PV & BESS StationIB VOGT UK LTDSolar + storage24030 Oct 2034Low30 Oct 2034Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 5 times: 3 later and 2 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026High Marnham Solar Farm1 Nov 202931 Oct 2031+24 months
13 Oct 2026High Marnham Solar Farm31 Oct 20311 Nov 2029-24 months
13 Oct 2026Morton Manor PV & BESS Station31 Oct 203730 Oct 2034-36 months
13 Oct 2026Mosedale Energy31 Mar 203331 Oct 2033+7 months
28 Jul 2026High Marnham (Tertiary)31 Oct 202931 Oct 2030+12 months

Thinking of connecting near High Marnham 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.