Staythorpe 400kV: grid connection queue
Staythorpe 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,637 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 May 2027 to 31 Oct 2030.
3projects in the queue
1,637 MWwaiting to connect
1,752 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,237 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Flash Solar Farm | ELEMENTS GREEN TRENT LTD | Solar + storage | 800 | 31 May 2027 | High | 30 May 2029 | Consents Approved | none |
| Staythorpe (BESS and PV) | SSE STAYTHORPE POWER LIMITED | Solar + storage | 437 | 29 Sep 2028 | High | 29 Sep 2030 | Consents Approved | none |
| Staythorpe | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Staythorpe 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Staythorpe 400kv: 250 MW waiting
- High Marnham 400kV: 3,596 MW waiting
- Cottam 400kV: 2,100 MW waiting
- Coddington 400kV: 2,240 MW waiting
- West Burton 400kV: 1,080 MW waiting