Staythorpe 400kV: grid connection queue

Staythorpe 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,637 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 May 2027 to 31 Oct 2030.

3projects in the queue
1,637 MWwaiting to connect
1,752 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,237 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Flash Solar FarmELEMENTS GREEN TRENT LTDSolar + storage80031 May 2027High30 May 2029Consents Approvednone
Staythorpe (BESS and PV)SSE STAYTHORPE POWER LIMITEDSolar + storage43729 Sep 2028High29 Sep 2030Consents Approvednone
StaythorpeENSO GREEN HOLDINGS X LIMITEDSolar + storage40031 Oct 2030Medium31 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Staythorpe 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points