West Burton 400kV: grid connection queue

West Burton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,080 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2029.

2projects in the queue
1,080 MWwaiting to connect
1,333 MWalready connected
480 MWholding Gate 2
1date moves since 2 Jun 2026
480 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
West Burton Solar ProjectWEST BURTON SOLAR PROJECT LIMITEDSolar + storage48031 Oct 2028High31 Oct 2030Consents Approved2
Steeple Solar FarmSteeple Solar Farm LimitedSolar + storage60031 Oct 2029Medium31 Oct 2029Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
27 Oct 2026West Burton Solar Project30 Nov 202831 Oct 2028-1 months

Thinking of connecting near West Burton 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.