West Burton 400kV: grid connection queue
West Burton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,080 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| West Burton Solar Project | WEST BURTON SOLAR PROJECT LIMITED | Solar + storage | 480 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | 2 |
| Steeple Solar Farm | Steeple Solar Farm Limited | Solar + storage | 600 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | West Burton Solar Project | 30 Nov 2028 | 31 Oct 2028 | -1 months |
Thinking of connecting near West Burton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Burton 132kV: 120 MW waiting
- Trent Valley North Connection Node B 132kV: 490 MW waiting
- Coddington 400kV: 2,240 MW waiting
- High Marnham 400kV: 3,596 MW waiting
- Cottam 400kV: 2,100 MW waiting