Staythorpe 400kv: grid connection queue
Staythorpe 400kv · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2030 to 30 Sep 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Field Farm | Net Zero One Ltd | Battery storage | 250 | 30 Sep 2030 | Medium | 30 Sep 2030 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Field Farm | 31 Oct 2030 | 30 Sep 2030 | -1 months |
Thinking of connecting near Staythorpe 400kv?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Staythorpe 400kV: 1,637 MW waiting
- High Marnham 400kV: 3,596 MW waiting
- Cottam 400kV: 2,100 MW waiting
- Coddington 400kV: 2,240 MW waiting
- West Burton 400kV: 1,080 MW waiting