Staythorpe 400kv: grid connection queue

Staythorpe 400kv · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2030 to 30 Sep 2030.

1project in the queue
250 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Field FarmNet Zero One LtdBattery storage25030 Sep 2030Medium30 Sep 2030Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Field Farm31 Oct 203030 Sep 2030-1 months

Thinking of connecting near Staythorpe 400kv?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points