Navenby 400kV: grid connection queue

Navenby 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

7 projects with 4,370 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2035.

7projects in the queue
4,370 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
SpringwellSPRINGWELL ENERGYFARM LIMITEDSolar + storage1,60030 Oct 2029Medium30 Oct 2029Scopingnone
Housham PV & BESSFOSSE GREEN ENERGY LIMITEDSolar + storage24030 May 2033Low30 May 2033Scopingnone
Navenby GEC (Ethos Green)NAVENBY GREEN ENERGY CENTRE LTDSolar + storage58030 Oct 2033Low30 Oct 2033Awaiting Consents1
Bicker DroveREWE 1 LIMITEDBattery storage40030 May 2034Low30 May 2034Scoping1
Cliff Hill Energy FarmRenewable Energy Systems LimitedSolar + storage80030 Oct 2034Low30 Oct 2034Scoping1
Bicker Fen BESSO&G Solar (SPV 40) LimitedSolar + storage25030 Oct 2034Low30 Oct 2034Scopingnone
EwerbyLeoda Solar Farm LimitedSolar + storage50030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Ewerby30 Oct 202930 Oct 2035+72 months

Thinking of connecting near Navenby 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.