Bicker Fen 400kV: grid connection queue

Bicker Fen 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,114 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 27 Jul 2026 to 1 Jun 2029.

4projects in the queue
1,114 MWwaiting to connect
0 MWalready connected
57 MWholding Gate 2
2date moves since 2 Jun 2026
400 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bicker Fen 2 SolarAGR SOLAR 3 LIMITEDSolar + storage5727 Jul 2026n/aAwaiting Consentsnone
Bicker Fen 1 SolarAGR SOLAR 2 LIMITEDSolar + storage5731 Oct 2026n/aUnder Construction/Commissioning2
Heckington Fen Solar ParkEcotricity (Heck Fen Solar) LimitedSolar + storage4001 Oct 2028High1 Oct 2030Scopingnone
Bicker Fenn Energy ParkBEACON FEN ENERGY PARK LIMITEDSolar + storage6001 Jun 2029Medium1 Jun 2029Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Bicker Fen 1 Solar1 Apr 20351 Apr 2033-24 months
20 Oct 2026Bicker Fen 1 Solar26 Sep 202531 Oct 2026+13 months

Thinking of connecting near Bicker Fen 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.