Bicker Fen: grid connection queue
Bicker Fen GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 240 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2033.
1project in the queue
240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Temple Oaks Renewable Energy Park | RIDGE CLEAN ENERGY LTD | Solar + storage | 240 | 30 Oct 2033 | Low | 30 Oct 2033 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Bicker Fen?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bicker Fen 400kV: 1,114 MW waiting
- Lincolnshire Coastal Node 400kV: 1,500 MW waiting
- Lincolnshire Coastal Node B 400kV: 800 MW waiting
- Navenby 400kV: 4,370 MW waiting
- Navenby 132kV: 529 MW waiting