Navenby 132kV: grid connection queue

Navenby 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 529 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2039.

3projects in the queue
529 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Forepower Lincoln (250) LtdFOREFUTURE ENERGY LTDBattery storage24030 Oct 2034Low30 Oct 2034Scoping1
Denton Estate Solar PV and BESSELGIN ENERGY ES CO LIMITEDSolar + storage12930 Oct 2034Low30 Oct 2034Scoping1
Vicarage Drove BESS LimitedVICARAGE DROVE BESS LIMITEDBattery storage16030 Oct 2039Low30 Oct 2039Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Denton Estate Solar PV and BESS30 Oct 203330 Oct 2034+12 months

Thinking of connecting near Navenby 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.