Navenby 132kV: grid connection queue
Navenby 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 529 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2039.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Forepower Lincoln (250) Ltd | FOREFUTURE ENERGY LTD | Battery storage | 240 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Denton Estate Solar PV and BESS | ELGIN ENERGY ES CO LIMITED | Solar + storage | 129 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
| Vicarage Drove BESS Limited | VICARAGE DROVE BESS LIMITED | Battery storage | 160 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Denton Estate Solar PV and BESS | 30 Oct 2033 | 30 Oct 2034 | +12 months |
Thinking of connecting near Navenby 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Navenby 400kV: 4,370 MW waiting
- Spalding North 400kV: 550 MW waiting
- Bicker Fen 400kV: 1,114 MW waiting
- Bicker Fen: 240 MW waiting
- Weston Marsh 400kV: 2,730 MW waiting