Spalding North 400kV: grid connection queue
Spalding North 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 550 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 30 Oct 2030 to 30 Oct 2030.
1project in the queue
550 MWwaiting to connect
1,250 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Spalding Energy Expansion | SPALDING ENERGY EXPANSION LIMITED | Mixed and other | 550 | 30 Oct 2030 | Medium | 30 Oct 2030 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Spalding North 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Weston Marsh 400kV: 2,730 MW waiting
- Navenby 132kV: 529 MW waiting
- Navenby 400kV: 4,370 MW waiting
- Lapwing Fen II (Walpole) IDNO: 250 MW waiting
- Walpole 400kV: 2,917 MW waiting