Walpole 400kV: grid connection queue

Walpole 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 2,917 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 1 Aug 2025 to 30 Jun 2033.

3projects in the queue
2,917 MWwaiting to connect
850 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Walpole 1 (Tertiary)WALPOLE GREEN LIMITEDSolar + storage571 Aug 2025n/aScopingnone
Norfolk001EPL NEWCO1 LIMITEDSolar + storage86030 Nov 2031Low30 Nov 2031Scopingnone
Walpole Flexible GenerationFLEXIBLE GENERATION 1 LTDMixed and other2,00030 Jun 2033Low30 Jun 2033Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
21 Jul 2026Walpole Grid Services Facility30 May 202513 Jul 2026+13 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Stickfast Ln Primary 11kVUK Power Networks3.4 km1.2 MW-0.9 MW
Leverington Primary 11kVUK Power Networks10.3 km22 MW6.5 MW
Walsoken Grid 11kVUK Power Networks11.2 km21 MW9.6 MW
Walsoken Grid 33kVUK Power Networks11.2 km70 MW48 MW
Wiggenhall Primary 11kVUK Power Networks11.7 km1.3 MW1.9 MW
Wisbech Railway Primary 11kVUK Power Networks12.0 km16 MW1 MW

Thinking of connecting near Walpole 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.