Walpole 132kV: grid connection queue

Walpole 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.

1project in the queue
100 MWwaiting to connect
660 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
100 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Walpole 2 (tertiary)ENSO GREEN HOLDINGS R LIMITEDSolar + storage10031 Oct 2027High30 Oct 2029Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Stickfast Ln Primary 11kVUK Power Networks1.4 km1.2 MW-0.9 MW
Leverington Primary 11kVUK Power Networks6.9 km22 MW6.5 MW
Walsoken Grid 11kVUK Power Networks7.5 km21 MW9.6 MW
Walsoken Grid 33kVUK Power Networks7.5 km70 MW48 MW
Wisbech Railway Primary 11kVUK Power Networks8.4 km16 MW1 MW
Wiggenhall Primary 11kVUK Power Networks10.6 km1.3 MW1.9 MW

Thinking of connecting near Walpole 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points