Lapwing Fen II (Walpole) IDNO: grid connection queue
Lapwing Fen II (Walpole) IDNO Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lapwing Fen II | ECLIPSE POWER NETWORKS LIMITED | Battery storage | 250 | 30 Oct 2029 | Medium | 30 Oct 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stickfast Ln Primary 11kV | UK Power Networks | 3.2 km | 1.2 MW | -0.9 MW |
| Leverington Primary 11kV | UK Power Networks | 5.6 km | 22 MW | 6.5 MW |
| Walsoken Grid 11kV | UK Power Networks | 7.1 km | 21 MW | 9.6 MW |
| Walsoken Grid 33kV | UK Power Networks | 7.1 km | 70 MW | 48 MW |
| Wisbech Railway Primary 11kV | UK Power Networks | 7.6 km | 16 MW | 1 MW |
| Outwell Moors Primary 11kV | UK Power Networks | 11.7 km | 5.1 MW | 2.1 MW |
Thinking of connecting near Lapwing Fen II (Walpole) IDNO?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Walpole 132kV: 100 MW waiting
- Walpole 400kV substations: 7 MW waiting
- Walpole 400kV: 2,917 MW waiting
- Weston Marsh 400kV: 2,730 MW waiting
- Spalding North 400kV: 550 MW waiting