Walpole 400kV substations: grid connection queue
Walpole 400kV substations · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 7 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2030 to 30 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Walpole | HOLLYGREEN ENERGYFARM LIMITED | Solar + storage | 7.1 | 30 Oct 2030 | Medium | 30 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stickfast Ln Primary 11kV | UK Power Networks | 1.4 km | 1.2 MW | -0.9 MW |
| Leverington Primary 11kV | UK Power Networks | 6.9 km | 22 MW | 6.5 MW |
| Walsoken Grid 11kV | UK Power Networks | 7.5 km | 21 MW | 9.6 MW |
| Walsoken Grid 33kV | UK Power Networks | 7.5 km | 70 MW | 48 MW |
| Wisbech Railway Primary 11kV | UK Power Networks | 8.4 km | 16 MW | 1 MW |
| Wiggenhall Primary 11kV | UK Power Networks | 10.6 km | 1.3 MW | 1.9 MW |
Thinking of connecting near Walpole 400kV substations?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Walpole 132kV: 100 MW waiting
- Lapwing Fen II (Walpole) IDNO: 250 MW waiting
- Walpole 400kV: 2,917 MW waiting
- Weston Marsh 400kV: 2,730 MW waiting
- Spalding North 400kV: 550 MW waiting