Weston Marsh 400kV: grid connection queue

Weston Marsh 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 2,730 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 30 Nov 2030 to 30 Jul 2033.

3projects in the queue
2,730 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
GT R4 Offshore Wind FarmGT R4 LIMITEDOffshore wind1,50030 Nov 2030Medium30 Nov 2030Scopingnone
Meridian Solar FarmMERIDIAN SOLAR FARM LIMITEDSolar + storage75030 Jun 2033Low30 Jun 2033Scoping1
Spalding PV and BESS StationETP UK 1 LTDSolar + storage48030 Jul 2033Low30 Jul 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Leverington Primary 11kVUK Power Networks18.6 km22 MW6.5 MW
Guyhirn Primary 11kVUK Power Networks18.9 km1.4 MW-0.7 MW
Peterborough East Grid 11kVUK Power Networks19.1 km99 MW25 MW

Thinking of connecting near Weston Marsh 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points