Five Estuaries 220/66 kV Offshore: grid connection queue
Five Estuaries 220/66 kV Offshore Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 1,080 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Five Estuaries Offshore Wind Farm | FIVE ESTUARIES OFFSHORE WIND FARM LIMITED | Offshore wind | 1,080 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Langley Av Primary 11kV | UK Power Networks | 0.9 km | 10 MW | 10 MW |
| Dock Rd Primary 11kV | UK Power Networks | 2.0 km | 19 MW | 9.8 MW |
| Felixstowe Grid 33kV | UK Power Networks | 2.6 km | 92 MW | 62 MW |
| Dovercourt Primary 11kV | UK Power Networks | 6.3 km | 14 MW | 7.8 MW |
| Shotley Primary 11kV | UK Power Networks | 6.7 km | 18 MW | 16 MW |
| Martlesham Primary 11kV | UK Power Networks | 11.9 km | 14 MW | 2.5 MW |
Thinking of connecting near Five Estuaries 220/66 kV Offshore?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramford 400kV: 1,163 MW waiting
- Bramford B 400kV: 650 MW waiting
- Hadleigh 400kV: 600 MW waiting
- Friston 400kV: 880 MW waiting
- Sizewell 400kV: 3,340 MW waiting