Bramford 400kV: grid connection queue

Bramford 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,163 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 16 Jul 2026 to 30 Jul 2033.

5projects in the queue
1,163 MWwaiting to connect
98 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bramford TertiaryBRAMFORD GREEN LIMITEDSolar + storage5716 Jul 2026n/aConsents Approvednone
Bramford BESSCSE33 LIMITEDBattery storage30030 Nov 2029Medium30 Nov 2029Consents Approvednone
Alcemi Bramford Battery Energy Storage FacilityALCEMI STORAGE DEVELOPMENTS 1 LIMITEDBattery storage50030 Oct 2030Medium30 Oct 2030Scoping1
Bramford 2 GEC (Ethos Green)BRAMFORD 2 GREEN ENERGY CENTRE LTDSolar + storage571 Jul 2032Low1 Jul 2032Awaiting Consentsnone
ER BRF 2 EnergyER PROJECT DEVELOPMENT CO LIMITEDSolar + storage24930 Jul 2033Low30 Jul 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Highfield Primary 11kVUK Power Networks4.5 km22 MW5.7 MW
Claydon Cement Primary 11kVUK Power Networks5.0 km6.2 MW7.7 MW
Ipswich Grid 11kVUK Power Networks5.3 km22 MW7 MW
Ipswich Grid 33kVUK Power Networks5.3 km73 MW17 MW
Gusford Hall Primary 11kVUK Power Networks5.8 km13 MW8 MW
Turret Ln Primary 11kVUK Power Networks6.5 km12 MW8.4 MW

Thinking of connecting near Bramford 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points