Hadleigh 400kV: grid connection queue
Hadleigh 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 600 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ardleigh Solar & BESS | Nembus BESS Limited | Solar + storage | 600 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Gusford Hall Primary 11kV | UK Power Networks | 6.0 km | 13 MW | 8 MW |
| Highfield Primary 11kV | UK Power Networks | 6.1 km | 22 MW | 5.7 MW |
| Ipswich Grid 11kV | UK Power Networks | 6.2 km | 22 MW | 7 MW |
| Ipswich Grid 33kV | UK Power Networks | 6.2 km | 73 MW | 17 MW |
| Claydon Cement Primary 11kV | UK Power Networks | 6.9 km | 6.2 MW | 7.7 MW |
| Turret Ln Primary 11kV | UK Power Networks | 7.4 km | 12 MW | 8.4 MW |
Thinking of connecting near Hadleigh 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramford 400kV: 1,163 MW waiting
- Bramford B 400kV: 650 MW waiting
- South Anglia Connection Node D 132kV: 400 MW waiting
- Five Estuaries 220/66 kV Offshore: 1,080 MW waiting
- South Anglia Connection Node A 400kV: 1,240 MW waiting