Bramford B 400kV: grid connection queue
Bramford B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 650 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Jun 2032 to 1 Jun 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bramford GEC (Ethos Green) | BRAMFORD GREEN ENERGY CENTRE LTD | Solar + storage | 650 | 1 Jun 2032 | Low | 1 Jun 2032 | Awaiting Consents | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Bramford GEC (Ethos Green) | 30 Oct 2033 | 1 Jun 2032 | -17 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Highfield Primary 11kV | UK Power Networks | 4.5 km | 22 MW | 5.7 MW |
| Claydon Cement Primary 11kV | UK Power Networks | 5.0 km | 6.2 MW | 7.7 MW |
| Ipswich Grid 11kV | UK Power Networks | 5.3 km | 22 MW | 7 MW |
| Ipswich Grid 33kV | UK Power Networks | 5.3 km | 73 MW | 17 MW |
| Gusford Hall Primary 11kV | UK Power Networks | 5.8 km | 13 MW | 8 MW |
| Turret Ln Primary 11kV | UK Power Networks | 6.5 km | 12 MW | 8.4 MW |
Thinking of connecting near Bramford B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramford 400kV: 1,163 MW waiting
- Hadleigh 400kV: 600 MW waiting
- Five Estuaries 220/66 kV Offshore: 1,080 MW waiting
- South Anglia Connection Node D 132kV: 400 MW waiting
- South Anglia Connection Node A 400kV: 1,240 MW waiting