Sizewell 400kV: grid connection queue

Sizewell 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 3,340 MW is waiting to connect here (largest by capacity: nuclear). Contracted dates run from 31 Jul 2035 to 31 Jul 2035.

1project in the queue
3,340 MWwaiting to connect
1,230 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sizewell CSizewell C LimitedNuclear3,34031 Jul 2035Low31 Jul 2035Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Leiston Primary 11kVUK Power Networks4.9 km8.6 MW4.1 MW
Benhall Primary 11kVUK Power Networks10.2 km11 MW5.9 MW
Peasenhall Primary 11kVUK Power Networks13.6 km6.3 MW1.1 MW
Orford Primary 11kVUK Power Networks13.6 km3.5 MW3.1 MW
Reydon Primary 11kVUK Power Networks14.1 km10 MW2.3 MW
Bentwaters Primary 11kVUK Power Networks16.1 km13 MW5.5 MW

Thinking of connecting near Sizewell 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points