Long Stratton 400kV: grid connection queue

Long Stratton 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2031 to 30 Oct 2031.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Long Stratton PV & BESS StationEAST PYE SOLAR LIMITEDSolar + storage50030 Oct 2031Medium30 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Hapton Primary 11kVUK Power Networks3.6 km20 MW9.1 MW
Tivetshall Primary 11kVUK Power Networks6.3 km14 MW3.8 MW
Mulbarton Primary 11kVUK Power Networks8.3 km5.2 MW1 MW
Harleston Primary 11kVUK Power Networks11.4 km8.1 MW4.9 MW
Wymondham Primary 11kVUK Power Networks11.9 km21 MW6.9 MW
Cringleford Primary 11kVUK Power Networks12.8 km9.7 MW0.9 MW

Thinking of connecting near Long Stratton 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points