North Anglia Connection Node E 400kV: grid connection queue
North Anglia Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
7 projects with 2,390 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Yaxley | CONNECTID 2 LIMITED | Solar + storage | 520 | 31 Oct 2034 | Low | 31 Oct 2034 | Awaiting Consents | none |
| Dove Solar | RWE Renewables UK Solar and Storage Limited | Solar + storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| EPL Suffolk | EPL NEWCO9 LIMITED | Solar + storage | 480 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Zenobe Yaxley BESS | ZENOBE ENERGY LIMITED | Battery storage | 300 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Lightsource Yaxley PV | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Yaxley BESS | Field Yaxley Ltd | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
| Noventum Yaxley | NOVENTUM POWER SOLAR 3 LIMITED | Solar + storage | 150 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | EPL Suffolk | 31 Oct 2032 | 31 Oct 2034 | +24 months |
| 20 Oct 2026 | EPL Suffolk | 31 Oct 2034 | 31 Oct 2032 | -24 months |
| 13 Oct 2026 | EPL Suffolk | 31 Oct 2032 | 31 Oct 2034 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Earlham Grid Local B 11kV | UK Power Networks | 5.2 km | 21 MW | 7.6 MW |
| Earlham Grid Local 11kV | UK Power Networks | 5.2 km | 25 MW | 5.6 MW |
| Earlham Grid 33kV | UK Power Networks | 6.3 km | 96 MW | 28 MW |
| Earlham West Primary 11kV | UK Power Networks | 6.3 km | 23 MW | 6.8 MW |
| Horsford Primary 11kV | UK Power Networks | 7.1 km | 17 MW | 7.6 MW |
| Cringleford Primary 11kV | UK Power Networks | 7.2 km | 9.7 MW | 0.9 MW |
Thinking of connecting near North Anglia Connection Node E 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Anglia Connection Node A 132kV: 813 MW waiting
- North Anglia Connection Node C 400kV: 2,450 MW waiting
- North Anglia Connection Node B 400kV: 3,000 MW waiting
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting
- Norwich Main 400kV: 4,484 MW waiting