North Anglia Connection Node B 400kV: grid connection queue

North Anglia Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 3,000 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

5projects in the queue
3,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Necton High Impact Energy HubTELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2034Low31 Oct 2034Scoping1
Greta IV (b)Greta IV LimitedSolar + storage50031 Oct 2034Low31 Oct 2034Scoping1
Greta IV (c)Greta IV LimitedBattery storage50031 Oct 2034Low31 Oct 2034Scoping1
Greta IV (d)Greta IV LimitedBattery storage50031 Oct 2034Low31 Oct 2034Scoping1
Project Number 4Greta IV LimitedSolar + storage50031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Greta IV (b)1 Mar 203131 Oct 2034+44 months
13 Oct 2026Greta IV (b)31 Oct 20341 Mar 2031-44 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Wymondham Primary 11kVUK Power Networks0.6 km21 MW6.9 MW
Hardingham Primary 11kVUK Power Networks5.8 km0.5 MW1.2 MW
Attleborough Primary 11kVUK Power Networks7.7 km20 MW4 MW
Hapton Primary 11kVUK Power Networks8.8 km20 MW9.1 MW
Mulbarton Primary 11kVUK Power Networks10.4 km5.2 MW1 MW
Cringleford Primary 11kVUK Power Networks10.7 km9.7 MW0.9 MW

Thinking of connecting near North Anglia Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points