North Anglia Connection Node B 400kV: grid connection queue
North Anglia Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 3,000 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Necton High Impact Energy Hub | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Greta IV (b) | Greta IV Limited | Solar + storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Greta IV (c) | Greta IV Limited | Battery storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Greta IV (d) | Greta IV Limited | Battery storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Project Number 4 | Greta IV Limited | Solar + storage | 500 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Greta IV (b) | 1 Mar 2031 | 31 Oct 2034 | +44 months |
| 13 Oct 2026 | Greta IV (b) | 31 Oct 2034 | 1 Mar 2031 | -44 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Wymondham Primary 11kV | UK Power Networks | 0.6 km | 21 MW | 6.9 MW |
| Hardingham Primary 11kV | UK Power Networks | 5.8 km | 0.5 MW | 1.2 MW |
| Attleborough Primary 11kV | UK Power Networks | 7.7 km | 20 MW | 4 MW |
| Hapton Primary 11kV | UK Power Networks | 8.8 km | 20 MW | 9.1 MW |
| Mulbarton Primary 11kV | UK Power Networks | 10.4 km | 5.2 MW | 1 MW |
| Cringleford Primary 11kV | UK Power Networks | 10.7 km | 9.7 MW | 0.9 MW |
Thinking of connecting near North Anglia Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node C 400kV: 2,450 MW waiting
- Long Stratton 400kV: 500 MW waiting
- North Anglia Connection Node A 400kV: 2,510 MW waiting
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting