North Anglia Connection Node A 400kV: grid connection queue
North Anglia Connection Node A 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 2,510 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2032 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norwich Main BESS | TASWAY ENERGY PARK LIMITED | Solar + storage | 950 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
| Noventum -Long Stratton | Noventum Power Solar 8 Limited | Solar + storage | 460 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Long Stratton 400 | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Long Stratton BESS | Field Long Stratton Ltd | Battery storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Swainsthorpe | Lightsource Renewable UK Development Limited | Solar + storage | 300 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Noventum -Long Stratton | 30 Oct 2038 | 31 Oct 2034 | -48 months |
| 13 Oct 2026 | Noventum -Long Stratton | 31 Oct 2034 | 30 Oct 2038 | +48 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| East Dereham Primary 11kV | UK Power Networks | 6.1 km | 13 MW | 13 MW |
| Hardingham Primary 11kV | UK Power Networks | 7.8 km | 0.5 MW | 1.2 MW |
| Watton Primary 11kV | UK Power Networks | 10.1 km | 22 MW | 2.5 MW |
| Weston Longville Primary 11kV | UK Power Networks | 12.9 km | 5.8 MW | 6.9 MW |
| Wymondham Primary 11kV | UK Power Networks | 13.5 km | 21 MW | 6.9 MW |
| Kempstone Primary 11kV | UK Power Networks | 13.8 km | -0.5 MW | 0.9 MW |
Thinking of connecting near North Anglia Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting
- Necton 400kV: 5,188 MW waiting
- North Anglia Connection Node B 400kV: 3,000 MW waiting
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node D 132kV: 478 MW waiting