Necton 400kV: grid connection queue
Necton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 5,188 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 31 Oct 2026 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Necton Greener Grid Park | Necton Grid Solutions Limited | Battery storage | 78 | 31 Oct 2026 | n/a | Consents Approved | none | |
| Vanguard | NORFOLK VANGUARD WEST LIMITED | Offshore wind | 1,320 | 31 Dec 2027 | High | 14 Jan 2030 | Consents Approved | 2 |
| Vanguard East | Norfolk Vanguard East Ltd | Offshore wind | 1,320 | 1 Apr 2028 | High | 16 Apr 2030 | Consents Approved | 2 |
| Norfolk Boreas | NORFOLK BOREAS LIMITED | Offshore wind | 1,320 | 1 Oct 2029 | Medium | 1 Oct 2029 | Awaiting Consents | none |
| Bradenham - Thetford (Necton) GEC (Ethos Green) | NECTON GREEN ENERGY CENTRE LTD | Solar + storage | 850 | 1 Oct 2033 | Low | 1 Oct 2033 | Scoping | 1 |
| Zenobe Necton BESS | ZENOBE ENERGY LIMITED | Battery storage | 300 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Vanguard East | 31 Dec 2027 | 1 Apr 2028 | +3 months |
| 20 Oct 2026 | Vanguard East | 1 Apr 2028 | 31 Dec 2027 | -3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Swaffham Grid 33kV | UK Power Networks | 5.1 km | 42 MW | 49 MW |
| Swaffham Grid 11kV | UK Power Networks | 5.2 km | 11 MW | 3.6 MW |
| Kempstone Primary 11kV | UK Power Networks | 6.4 km | -0.5 MW | 0.9 MW |
| Watton Primary 11kV | UK Power Networks | 8.8 km | 22 MW | 2.5 MW |
| East Dereham Primary 11kV | UK Power Networks | 12.0 km | 13 MW | 13 MW |
| Narborough Primary 11kV | UK Power Networks | 14.4 km | 11 MW | 5.2 MW |
Thinking of connecting near Necton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Swaffham 400KV: 500 MW waiting
- North Anglia Connection Node A 400kV: 2,510 MW waiting
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting
- Thetford 400kV: 720 MW waiting
- North Anglia Connection Node D 132kV: 478 MW waiting