North Anglia Connection Node D 132kV: grid connection queue
North Anglia Connection Node D 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 478 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Strawberry Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 278 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Walsoken Battery | Walsoken Limited | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Weston Longville Primary 11kV | UK Power Networks | 6.4 km | 5.8 MW | 6.9 MW |
| Sall Grid 33kV | UK Power Networks | 6.8 km | 85 MW | 25 MW |
| Sall 11kV | UK Power Networks | 6.9 km | 18 MW | 2.2 MW |
| East Dereham Primary 11kV | UK Power Networks | 10.7 km | 13 MW | 13 MW |
| Stody Primary 11kV | UK Power Networks | 13.8 km | 13 MW | 0.6 MW |
| Horsford Primary 11kV | UK Power Networks | 14.0 km | 17 MW | 7.6 MW |
Thinking of connecting near North Anglia Connection Node D 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting
- North Anglia Connection Node A 132kV: 813 MW waiting
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node A 400kV: 2,510 MW waiting
- Norwich Main 400kV: 4,484 MW waiting