Norwich Main 400kV: grid connection queue
Norwich Main 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 4,484 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 18 Dec 2025 to 30 Jun 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norwich | PIVOTED POWER LLP | Solar + storage | 57 | 18 Dec 2025 | n/a | Consents Approved | none | |
| Hornsea Power Station 3 | HORNSEA PROJECT THREE (UK) LIMITED | Offshore wind | 3,000 | 1 Oct 2026 | n/a | Consents Approved | none | |
| Norwich Yare | ASHGREEN ENERGYFARM LIMITED | Solar + storage | 50 | 24 Apr 2027 | High | 23 Apr 2029 | Consents Approved | 2 |
| Scira-Dudgeon Extension | SHERINGHAM SHOAL AND DUDGEON EXTENSIONS PROJCO LIMITED | Offshore wind | 1,350 | 1 Jan 2030 | Medium | 1 Jan 2030 | Scoping | none |
| Norwich 2 | EDF ENERGY RENEWABLES LIMITED | Mixed and other | 28 | 30 Jun 2033 | Low | 30 Jun 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| George Hill Primary 11kV | UK Power Networks | 1.7 km | 21 MW | 4.1 MW |
| Sprowston Primary 11kV | UK Power Networks | 1.8 km | 9.2 MW | 4.2 MW |
| Mousehold Primary 11kV | UK Power Networks | 3.2 km | 22 MW | 4.5 MW |
| Boundary Park Primary 11kV | UK Power Networks | 3.4 km | 13 MW | 7.4 MW |
| Barrack St Primary 11kV | UK Power Networks | 3.8 km | 20 MW | 11 MW |
| St Stephens Primary 11kV | UK Power Networks | 5.3 km | 38 MW | 14 MW |
Thinking of connecting near Norwich Main 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norwich Main 132kV: 100 MW waiting
- North Anglia Connection Node A 132kV: 813 MW waiting
- North Anglia Connection Node C 400kV: 2,450 MW waiting
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node B 400kV: 3,000 MW waiting