Norwich Main 132kV: grid connection queue
Norwich Main 132kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norwich 100MW BESS | FLEXION ENERGY SPV 2 LTD | Battery storage | 100 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| George Hill Primary 11kV | UK Power Networks | 1.7 km | 21 MW | 4.1 MW |
| Sprowston Primary 11kV | UK Power Networks | 1.8 km | 9.2 MW | 4.2 MW |
| Mousehold Primary 11kV | UK Power Networks | 3.2 km | 22 MW | 4.5 MW |
| Boundary Park Primary 11kV | UK Power Networks | 3.4 km | 13 MW | 7.4 MW |
| Barrack St Primary 11kV | UK Power Networks | 3.8 km | 20 MW | 11 MW |
| St Stephens Primary 11kV | UK Power Networks | 5.3 km | 38 MW | 14 MW |
Thinking of connecting near Norwich Main 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norwich Main 400kV: 4,484 MW waiting
- North Anglia Connection Node A 132kV: 813 MW waiting
- North Anglia Connection Node C 400kV: 2,450 MW waiting
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node B 400kV: 3,000 MW waiting