NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: grid connection queue
NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| GF Norwich BESS | GF Norwich Energy Ltd | Battery storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | GF Norwich BESS | 31 Oct 2032 | 31 Oct 2034 | +24 months |
| 20 Oct 2026 | GF Norwich BESS | 31 Oct 2034 | 31 Oct 2032 | -24 months |
| 13 Oct 2026 | GF Norwich BESS | 31 Oct 2032 | 31 Oct 2034 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Weston Longville Primary 11kV | UK Power Networks | 4.8 km | 5.8 MW | 6.9 MW |
| East Dereham Primary 11kV | UK Power Networks | 4.9 km | 13 MW | 13 MW |
| Hardingham Primary 11kV | UK Power Networks | 10.8 km | 0.5 MW | 1.2 MW |
| Sall 11kV | UK Power Networks | 12.8 km | 18 MW | 2.2 MW |
| Sall Grid 33kV | UK Power Networks | 12.9 km | 85 MW | 25 MW |
| Horsford Primary 11kV | UK Power Networks | 14.4 km | 17 MW | 7.6 MW |
Thinking of connecting near NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Anglia Connection Node D 132kV: 478 MW waiting
- North Anglia Connection Node A 400kV: 2,510 MW waiting
- North Anglia Connection Node E 400kV: 2,390 MW waiting
- North Anglia Connection Node A 132kV: 813 MW waiting
- North Anglia Connection Node B 400kV: 3,000 MW waiting