Thetford 400kV: grid connection queue

Thetford 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 720 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
720 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
J212 High Grove SolarRWE Renewables UK Solar and Storage LimitedSolar + storage72031 Oct 2031Medium31 Oct 2031Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Thetford Grid 33kVUK Power Networks4.2 km49 MW29 MW
Kimms Belt Primary 11kVUK Power Networks8.7 km12 MW2.5 MW
Brandon Primary 11kVUK Power Networks10.6 km8.9 MW1.1 MW
Thetford Grid 11kVUK Power Networks10.8 km9.6 MW2.8 MW
Watton Primary 11kVUK Power Networks11.5 km22 MW2.5 MW
Feltwell Primary 11kVUK Power Networks14.0 km2.5 MW0.2 MW

Thinking of connecting near Thetford 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points