Southery 400kV: grid connection queue

Southery 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 600 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2031 to 30 Oct 2031.

1project in the queue
600 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
SoutherySSE SOUTHERY SOLAR LIMITEDSolar + storage60030 Oct 2031Medium30 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Southery Primary 11kVUK Power Networks3.1 km-2.7 MW1.2 MW
Feltwell Primary 11kVUK Power Networks9.1 km2.5 MW0.2 MW
Littleport Primary 11kVUK Power Networks9.9 km-2.7 MW4.3 MW
Downham Market Primary 11kVUK Power Networks10.0 km9.8 MW2.3 MW
Northwold Primary 11kVUK Power Networks10.6 km18 MW9.1 MW
Upwell Lakes End Primary 11kVUK Power Networks12.1 km-2.7 MW1 MW

Thinking of connecting near Southery 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.