Swaffham 400KV: grid connection queue
Swaffham 400KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| The Droves (formerly Swaffham PV & BESS) | THE DROVES SOLAR FARM LIMITED | Solar + storage | 500 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Swaffham Grid 11kV | UK Power Networks | 1.7 km | 11 MW | 3.6 MW |
| Swaffham Grid 33kV | UK Power Networks | 1.7 km | 42 MW | 49 MW |
| Kempstone Primary 11kV | UK Power Networks | 7.7 km | -0.5 MW | 0.9 MW |
| Narborough Primary 11kV | UK Power Networks | 9.5 km | 11 MW | 5.2 MW |
| Watton Primary 11kV | UK Power Networks | 12.0 km | 22 MW | 2.5 MW |
| Lt Massingham Primary 11kV | UK Power Networks | 14.8 km | 1 MW | -0.1 MW |
Thinking of connecting near Swaffham 400KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Necton 400kV: 5,188 MW waiting
- North Anglia Connection Node A 400kV: 2,510 MW waiting
- Thetford 400kV: 720 MW waiting
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting
- Southery 400kV: 600 MW waiting