Swaffham 400KV: grid connection queue

Swaffham 400KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2033.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
The Droves (formerly Swaffham PV & BESS)THE DROVES SOLAR FARM LIMITEDSolar + storage50030 Oct 2033Low30 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Swaffham Grid 11kVUK Power Networks1.7 km11 MW3.6 MW
Swaffham Grid 33kVUK Power Networks1.7 km42 MW49 MW
Kempstone Primary 11kVUK Power Networks7.7 km-0.5 MW0.9 MW
Narborough Primary 11kVUK Power Networks9.5 km11 MW5.2 MW
Watton Primary 11kVUK Power Networks12.0 km22 MW2.5 MW
Lt Massingham Primary 11kVUK Power Networks14.8 km1 MW-0.1 MW

Thinking of connecting near Swaffham 400KV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.