Abham 132kV: grid connection queue
Abham 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stretchford Farm Solar and Storage | BSR APPLICATIONS LIMITED | Solar + storage | 100 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Abham 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Langage 400kV: 1,649 MW waiting
- Landulph 400kV: 57 MW waiting
- Tideford 400kV: 500 MW waiting
- SANDFORD B 400kV SUBSTATION: 600 MW waiting
- Exeter 400kV: 1,194 MW waiting