Landulph 400kV: grid connection queue
Landulph 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 57 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 18 May 2026 to 18 May 2026.
1project in the queue
57 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Landulph | PIVOTED POWER LLP | Solar + storage | 57 | 18 May 2026 | n/a | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Landulph 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Tideford 400kV: 500 MW waiting
- Langage 400kV: 1,649 MW waiting
- Pyworthy 400kV: 300 MW waiting
- Abham 132kV: 100 MW waiting
- Alverdiscott 400kV: 10,308 MW waiting