Alverdiscott 400kV: grid connection queue

Alverdiscott 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

13 projects with 10,308 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 31 Mar 2029 to 24 Apr 2037.

13projects in the queue
10,308 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
7date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Petroc Offshore Wind FarmBLUEFLOAT ENERGY UK HOLDINGS LIMITEDOffshore wind30031 Mar 2029Medium31 Mar 2029Scoping1
AlverdiscottPIVOTED POWER LLPBattery storage10031 Aug 2031Medium31 Aug 2031Scoping1
Merlin 2 Offshore WindfarmOFFSHORE WIND LIMITEDOffshore wind1,50031 Oct 2031Medium31 Oct 2031Scoping1
Celtic 2 Offshore Wind FarmRWE Offshore WindOffshore wind1,00031 Oct 2031Medium31 Oct 2031Scoping1
Gwynt Glas Offshore Wind FarmGWYNT GLAS OFFSHORE WIND FARM LIMITEDOffshore wind30031 Oct 2031Medium31 Oct 2031Scoping1
Merlin Offshore Wind FarmOFFSHORE WIND LIMITEDOffshore wind30031 Oct 2031Medium31 Oct 2031Scoping1
Morwind 300Morwind LtdOffshore wind30031 Oct 2031Medium31 Oct 2031Scoping1
SSE Celtic Sea 1SSE RENEWABLES OFFSHORE WINDFARM HOLDINGS LIMITEDOffshore wind1,5006 Dec 2036Low6 Dec 2036Scopingnone
Cormoran Offshore Wind FarmSouth West Wind Holdco LimitedOffshore wind1,0086 Dec 2036Low6 Dec 2036Scopingnone
Equinor Celtic Sea 1EQUINOR NEW ENERGY LIMITEDOffshore wind1,0006 Dec 2036Low6 Dec 2036Scoping1
Gwynt Glas Offshore Wind Farm 2GWYNT GLAS OFFSHORE WIND FARM LIMITEDOffshore wind1,0006 Dec 2036Low6 Dec 2036Scoping1
Petroc Extension Offshore Wind FarmBLUEFLOAT ENERGY UK HOLDINGS LIMITEDOffshore wind1,0006 Dec 2036Low6 Dec 2036Scopingnone
Alverdiscott FarmAlverdiscott 10 Renewables LtdSolar + storage1,00024 Apr 2037Low24 Apr 2037Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 7 times: 5 later and 2 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
3 Nov 2026Petroc Offshore Wind Farm31 Mar 202631 Mar 2029+36 months
20 Oct 2026Gwynt Glas Offshore Wind Farm6 Dec 203631 Oct 2031-61 months
20 Oct 2026Petroc Offshore Wind Farm6 Dec 203631 Mar 2026-128 months
13 Oct 2026Alverdiscott31 Oct 202931 Aug 2031+22 months
13 Oct 2026Gwynt Glas Offshore Wind Farm31 Oct 20316 Dec 2036+61 months
13 Oct 2026Petroc Offshore Wind Farm31 Mar 20296 Dec 2036+92 months
13 Oct 2026Merlin Offshore Wind Farm1 Nov 202830 Oct 2031+36 months

Thinking of connecting near Alverdiscott 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points