Alverdiscott 400kV: grid connection queue
Alverdiscott 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
13 projects with 10,308 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 31 Mar 2029 to 24 Apr 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Petroc Offshore Wind Farm | BLUEFLOAT ENERGY UK HOLDINGS LIMITED | Offshore wind | 300 | 31 Mar 2029 | Medium | 31 Mar 2029 | Scoping | 1 |
| Alverdiscott | PIVOTED POWER LLP | Battery storage | 100 | 31 Aug 2031 | Medium | 31 Aug 2031 | Scoping | 1 |
| Merlin 2 Offshore Windfarm | OFFSHORE WIND LIMITED | Offshore wind | 1,500 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| Celtic 2 Offshore Wind Farm | RWE Offshore Wind | Offshore wind | 1,000 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| Gwynt Glas Offshore Wind Farm | GWYNT GLAS OFFSHORE WIND FARM LIMITED | Offshore wind | 300 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| Merlin Offshore Wind Farm | OFFSHORE WIND LIMITED | Offshore wind | 300 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| Morwind 300 | Morwind Ltd | Offshore wind | 300 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| SSE Celtic Sea 1 | SSE RENEWABLES OFFSHORE WINDFARM HOLDINGS LIMITED | Offshore wind | 1,500 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | none |
| Cormoran Offshore Wind Farm | South West Wind Holdco Limited | Offshore wind | 1,008 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | none |
| Equinor Celtic Sea 1 | EQUINOR NEW ENERGY LIMITED | Offshore wind | 1,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| Gwynt Glas Offshore Wind Farm 2 | GWYNT GLAS OFFSHORE WIND FARM LIMITED | Offshore wind | 1,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| Petroc Extension Offshore Wind Farm | BLUEFLOAT ENERGY UK HOLDINGS LIMITED | Offshore wind | 1,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | none |
| Alverdiscott Farm | Alverdiscott 10 Renewables Ltd | Solar + storage | 1,000 | 24 Apr 2037 | Low | 24 Apr 2037 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 7 times: 5 later and 2 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Petroc Offshore Wind Farm | 31 Mar 2026 | 31 Mar 2029 | +36 months |
| 20 Oct 2026 | Gwynt Glas Offshore Wind Farm | 6 Dec 2036 | 31 Oct 2031 | -61 months |
| 20 Oct 2026 | Petroc Offshore Wind Farm | 6 Dec 2036 | 31 Mar 2026 | -128 months |
| 13 Oct 2026 | Alverdiscott | 31 Oct 2029 | 31 Aug 2031 | +22 months |
| 13 Oct 2026 | Gwynt Glas Offshore Wind Farm | 31 Oct 2031 | 6 Dec 2036 | +61 months |
| 13 Oct 2026 | Petroc Offshore Wind Farm | 31 Mar 2029 | 6 Dec 2036 | +92 months |
| 13 Oct 2026 | Merlin Offshore Wind Farm | 1 Nov 2028 | 30 Oct 2031 | +36 months |
Thinking of connecting near Alverdiscott 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pyworthy 400kV: 300 MW waiting
- SANDFORD B 400kV SUBSTATION: 600 MW waiting
- Exeter 400kV: 1,194 MW waiting
- Exeter Main 400kV: 249 MW waiting
- Landulph 400kV: 57 MW waiting