Exeter 400kV: grid connection queue

Exeter 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,194 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 1 May 2024 to 28 Oct 2033.

4projects in the queue
1,194 MWwaiting to connect
0 MWalready connected
680 MWholding Gate 2
0date moves since 2 Jun 2026
737 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Exeter Main TertiaryEXETER MAIN BATTERY LIMITEDGas and thermal571 May 2024n/aScoping1
Exeter BESSExeter Storage LimitedBattery storage68030 Aug 2027High29 Aug 2029Consents Approved2
Exeter (Tertiary)PIVOTED POWER LLPSolar + storage5716 Jun 2028High16 Jun 2030Awaiting Consentsnone
Exeter MainENSO GREEN HOLDINGS X LIMITEDSolar + storage40028 Oct 2033Low28 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Exeter 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points