Exeter 400kV: grid connection queue
Exeter 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,194 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 1 May 2024 to 28 Oct 2033.
4projects in the queue
1,194 MWwaiting to connect
0 MWalready connected
680 MWholding Gate 2
0date moves since 2 Jun 2026
737 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Exeter Main Tertiary | EXETER MAIN BATTERY LIMITED | Gas and thermal | 57 | 1 May 2024 | n/a | Scoping | 1 | |
| Exeter BESS | Exeter Storage Limited | Battery storage | 680 | 30 Aug 2027 | High | 29 Aug 2029 | Consents Approved | 2 |
| Exeter (Tertiary) | PIVOTED POWER LLP | Solar + storage | 57 | 16 Jun 2028 | High | 16 Jun 2030 | Awaiting Consents | none |
| Exeter Main | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 28 Oct 2033 | Low | 28 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Exeter 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Exeter Main 400kV: 249 MW waiting
- SANDFORD B 400kV SUBSTATION: 600 MW waiting
- Taunton 400kV: 100 MW waiting
- Axminster 132kV: 590 MW waiting
- Axminster 400kV: 50 MW waiting